Campus Updates

April 8, 2018

2019.04.05 ProCore (3).jpeg    2019.04.05 ProCore (4).jpeg

Tile work has begun in the Behavioral Health Care Center bathrooms. We are loving the results!

April 5, 2019

2019.04.05 ProCore (1).jpeg   2019.04.05 ProCore (2).jpeg

Looking forward to having our youth wake up to these views. 

March 26, 2019

The City of Albany approved the amendment to the district plan for the RTC project and issued a negative declaration on the SEQR. Construction is scheduled to begin Summer 2019. 

March 25, 2019

pipes and rossetti tour 3.25.19  (24).JPG  pipes and rossetti tour 3.25.19  (26).JPG

The Campus Project Youth Ambassadors meet weekly with BBL site supervisor and other contractors onsite to learn about the Behavioral Health Care Project. Their ideas and questions,  keep the project team on our toes!

 

March 20, 2019

pipes and rossetti tour 3.25.19  (8).JPG  pipes and rossetti tour 3.25.19  (6).JPG

Galusha & Sons will be onsite for the next 2 weeks to update our storm management system. While this work occurs, construction parking has been displaced to Academy Road. As always if you have questions or concerns, please email Northern Rivers' Project Manager at This email address is being protected from spambots. You need JavaScript enabled to view it.

 

March 11, 2019

 inside updates 3.11.19  (7).JPG   inside updates 3.11.19  (15).JPG

This week painters will be on-site to begin priming the walls of the Behavioral Health Care Center. 

February 26, 2019

The Residential Treatment Center project was presented to the City of Albany Planning Board, Tuesday, February 26.  We anticipate having approval  March 26th.

February 22, 2019

siding 2.21.19  (17).JPG   siding 2.21.19  (33).JPG

Exterior trim and siding work continues on the Behavioral Health Care Center. 

February 8, 2019

Ambassadors 02.04.2019  (29).JPG   sheet rock 02.11.19  (6).JPG

Door frames and drywall installation continues in the Behavioral Health Care Center. Electrical circuits for rooms and lighting have been installed. Exterior Trim and Siding work will begin next week. 

January 29, 2019

inside pics 1.29.19  (4).JPG  inside pics 1.29.19  (9).JPG

Installation of PVC window trim and molding continues. With the completion of the window trim, the siding and brickwork can begin. Plywood backing is currently being installed. The sheetrock and ceilings will be added in the next few weeks.